relocation of a Compressor and Dehydration Station from Fort Nelson, BC to Fort St. John, BC
General Mechanical Contractor
Structural upgrades to modularize off-module piping in Fort Nelson, to make piping and structural steel suitable for transportation as assembled modules
Disassembly of all interconnect piping between equipment and piping modules
Unload and setting of same equipment at Fort St. John site
Fabrication, assembly and installation of 6 new modules
Construction of a pump station on a NPS 24 pipeline
Mechanical contractor
Cut and cap piles
Excavating for pump foundation and pouring concrete
Fabrication and installation of structural steel and pipe rack modules